Recommendation 93-4, Environmental Restoration Management Contracts
93-4 BY YEAR:
1996 1995 1994 1993
This page last updated Wednesday, December 8, 2004
Key Documents & Information
- Board Recommendation: from Chairman Conway to Secretary O'Leary, dated June 16, 1993.
- Department Response: from Secretary O'Leary to Chairman Conway, August 6, 1993.
- Department Implementation Plan: dated November 5, 1993.
- Department Closure Proposal: dated March 12, 1996.
- Board Closure: dated June 28, 1996.
Chronicle of Related Correspondence
1996
- June 28, 1996, Board letter accepting the Department's proposal to close 93-4 implementation plan.
- March 12, 1996, Department letter forwarding the ninth Quarterly Status Report for 93-4implementation plan.
- January 30, 1996, Board letter forwarding comments regarding Department's commitment to revise FAR Manual.
- January 17, 1996, Department letter responding to Board request to revise 93-4 implementation plan.
1995
- December 1, 1995, Department letter forwarding the eighth Quarterly Status Report for 93-4 implementation plan.
- October 4, 1995, Board letter acknowledging receipt of Department's seventh quarterly report for 93-4 implementation plan.
- September 28, 1995, Department letter transmitting generic Technical Management Plan, as a part of 93-4 implementation plan.
- August 14, 1995, Board letter forwarding comments on the revised Department Order 430.1, "Life Cycle Assets Management," as a part of the 93-4 implementation plan.
- June 27, 1995, Department letter discussing improvements to Department's Project Management Order, 4700.1, as a part of the 93-4 implementation plan.
- May 5, 1995, Department letter forwarding the sixth Quarterly Status Report for 93-4 implementation plan.
- February 3, 1995, Board letter noting major deficiencies with the proposed revision of DOE Order 4700.1.
1994
- July 28, 1994, Department letter forwarding the third Quarterly Status Report for 93-4 implementation plan.
- May 16, 1994, Department letter providing report addressing sub-recommendation 4 and address the recent root problems at Fernald Site.
- April 28, 1994, Department letter forwarding the second Quarterly Status Report for 93-4 implementation plan.
- April 11, 1994, Department forwards charter of task force set up to revise the Technical Management Plan for 93-4 implementation plan.
- April 4, 1994, Department letter forwarding its "Making Contracting Work Better" report, signed by Guimond for Assistant Secretary Grumbly.
1993
- November 18, 1993, Board letter acknowledging receipt of Recommendation 93-4 Implementation Plan.
- November 5, 1993, Department letter forwarding 93-4 Implementation Plan.
- August 6, 1993, Department letter accepting Recommendation 93-4.
- June 16, 1993, Board letter forwarding Recommendation 93-4, Environment Restoration Management Contracts.