Recommendation 99-1, Safe Storage of Fissionable Material called "Pits
99-1 BY YEAR:
2005 2004 2003 2002 2001 2000 1999
This page last updated Tuesday, February 26, 2013
Key Documents & Information
- Board Recommendation: from Chairman Conway to Secretary Richardson, dated August 11, 1999.
- Department Response: from Secretary Richardson to Chairman Conway, dated October 12, 1999.
- Department Implementation Plan: dated February 1, 2000.
- Board Closure: dated September 9, 2005.
Chronicle of Related Correspondence
- September 9, 2005, Board letter establishing an annual reporting requirement regarding the Pit Management Plan (PMP) and the pit packaging program at Pantex and closing Recommendation 99-1, Safe Storage of Fissionable Material Called "Pits".
- August 8, 2005, Department letter forwarding the Final Report regarding the 99-1 implementation plan, Safe Storage of Fissionable Materials Called "Pits", and proposing closure of the 99-1 recommendaton.
- No document links for 2004
- No document links for 2003
- May 8, 2002, Board letter regarding the Department's revision to the Implementation Plan for Board recommendation 99-1, Safe Storage of Fissionable Material Called "Pits."
- March 18, 2002, Department letter informing the Board of the Department's intent to change commitment 5.2.1 in Implementation Plan 99-1 regarding the safe storage of pits at the Pantex Plant.
- February 28, 2002, Department letter enclosing the Pantex Plant Sealed Insert First Quarter Fiscal Year 2002 Summary Status Report, a deliverable under Commitment 5.2.2 of the 99-1 Implementation Plan.
2001
- March 15, 2001, Department letter enclosing the AL-R8 Sealed Insert pit repackaging status report for the 1st Quarter of FY 2001 in accordance with Implementation Plan 99-1.
- January 11, 2001, Department letter enclosing the AL-R8 Sealed Insert Container Surveillance Report for Fiscal Year 2000, a deliverable in the 99-1 Implementation Plan.
2000
- December 1, 2000, Department letter enclosing a report on Pantex Pit Management Plan, a deliverable under Commitment 5.2.3 of Implementation Plan 99-1.
- November 17, 2000, Department letter enclosing a copy of the Final Change Order (FCO) for Inconel 718 capscrews to replace carbon steel capscrews in AL-R8 Sealed Insert, a deliverable under Commitment 5.1.1 of Implementation Plan 99-1.
- August 18, 2000, Department letter forwarding a copy of the Pantex Plant Sealed Insert Third Quarter FY 2000 Summary Status Report, a deliverable under Commitment 5.2.2 of implementation plan 99-1. [HTML]
- July 7, 2000, Board letter regarding budget concerns that may preclude the Department from meeting its commitments in Implementation Plan 99-1.
- April 7, 2000, Board letter acknowledging receipt of and accepting the Department's proposed implementation plan for 99-1.
- March 27, 2000, Department letter forwarding the Department's pit storage container surveillance program plan. This is a deliverable under Commitment 5.3.1 of implementation plan 99-1.
- February 23, 2000, Department letter forwarding the amended Work Authorization Directive (WAD) for pit repackaging at the Pantex Plant. It is also a deliverable under Commitment 5.2.1 of the Department's 99-1 Implementation Plan.
- February 1, 2000, Department letter forwarding DOE's Implementation Plan for Board Recommendation 99-1, Safe Storage of Pits at Pantex.